Power Plants – Delay Claims

Power Plants – Delay Claims:

Michael supported a major mechanical contractor with the planning and subsequent delay claims analysis of a $2B construction of a natural gas-fired plant to replace an outdated coal-fired plant on the same site.

Michael developed a detailed baseline and incorporated installation of major mechanical equipment, to meet interim contract milestone dates, including:

  • 2x Gas Turbine, Generator and auxiliaries for U5 and U6

    Power Plants - Delay Claims

    Power Plants – Delay Claims

  • 2x Steam Turbine, Generator and auxiliaries for U5 and U6
  • 2x Heat Recovery Steam Generator (HRSG) for U5 and U6
  • 1x Air Cooler Condenser (ACC)

Michael developed monthly progress updates and detailed narratives identifying:

  • Status of current and projected status of the work
  • Status of contract milestone dates
  • Primary and near critical paths
  • Anticipated equipment delivery dates by others
  • Impeded access, by others,  to progress critical path work
  • Current and projected labor demands
  • Open RFIs and analysis of singular and cumulative impacts to critical path work
  • Interference/discrepancies of installed components, by others, and analysis of singular and cumulative impacts to critical path work

Michael, also, developed:

  • Requests for time extensions
  • Requests for Equitable Adjustments (REAs), and
  • Time Impact Analysis (TIA) to support entitlement