Central/Artery Tunnel Project - Logan Airport Interchange, Boston, MA, Project Value: $240M
Alternative Dispute Resolution (ADR Support) - Construction Risk Consultants were retained by the
general contractor to perform forensic analysis of all project
documentation including: contract documents, correspondence,
financial records and schedules.
The contract included construction of at-grade and elevated
roadways, bridges, tunnels and boat sections. The project
also contained more than a dozen interim staging configurations
providing access and egress to and from Logan airport, one
of the ten busiest airports nationwide.
Construction Risk Consultants worked closely with the project team and developed
all necessary documentation to support the entitlement of
a substantial claim for damages caused due to unanticipated
ground conditions and other interferences causing major schedule delays. As the owner failed
to respond proactively to requests to extend the contract milestone
dates, the general contractor was forced to constructively
accelerate the remaining work, resulting in significant additional costs.
Construction Risk Consultants supported the project team, every step of the
way, providing additional documentation, as requested by the
owner. The principal successfully negotiated and settled the claim.
|